Electrifying Maritime’s Heavy Logistics with High-Power Truck Charging
18 High-powered chargers
Deployed across three major UK logistics hubs
36 Electric trucks
Enabled for simultaneous charging
5 MW
Installed capacity supporting scalable nationwide electrification
Challenge
Maritime Transport operates one of the UK’s largest integrated road and rail freight networks, with 41 sites, nine strategic rail terminals and a fleet of 1,600 trucks.
As part of its commitment to operating the cleanest, most sustainable full-load supply chain in the country, Maritime needed to electrify heavy logistics operations at scale — starting with its highest-duty truck hubs.
The challenge was to:
- Deploy high-power charging capable of supporting battery-electric HGVs
- Integrate infrastructure into live logistics operations
- Ensure sufficient grid capacity for high-load charging
- Create a scalable foundation for nationwide fleet electrification
This required more than hardware, it required an integrated electrification strategy aligned with long-term fleet rollout.
Solution
Maritime appointed VEV to deliver the first phase of truck-charging infrastructure across three major UK logistics hubs.
VEV deployed:
- 18 high-powered chargers
- Unit capacities ranging from 100 kW to 1 MW
- A total installed capacity of 5 MW
- Infrastructure enabling simultaneous charging for up to 36 electric trucks
The deployment formed part of VEV’s end-to-end electrification solution, integrating site design, power systems, grid integration, charging hardware, software and ongoing optimisation.
The first sites electrified include Wakefield, Tilbury and Doncaster, supporting Maritime’s rollout of battery-electric trucks entering service.
"The partnership between VEV and Maritime has grown into a strong, high-performing relationship. They’ve been our trusted experts throughout our high-powered electrification journey. My experience with VEV has been very positive — the team’s expertise, commitment, and genuine passion align perfectly with Maritime’s own bold ambitious electrification plans"
Outcome
The project delivered:
- High-power infrastructure installed across three depots
- Charging capacity aligned with heavy-duty logistics operations
- A foundation for nationwide electrification
- Integrated software and optimisation ensuring operational reliability
- Strengthened long-term partnership between VEV and Maritime
No two fleets are the same
If you're ready to take the next step, contact us today and find out how we can accelerate your electrification ambitions.
Project Gallery
Detail
The deployment marks Maritime’s first major electrification of zero-emission HGV operations, supporting its strategy to own and operate the cleanest full-load supply chain in the UK.
By combining high-capacity infrastructure with integrated power systems and optimisation software, the solution provides immediate operational capability, scalable expansion potential, and reliable performance under high-duty cycles.
This project demonstrates how high-power charging infrastructure can be integrated into live heavy-logistics environments — without compromising operational efficiency